Project:
Replacement of Petersberg tunnel

Service period:
2016 – 2020

Project client:
Work group Petersberg tunnel, c/o Marti GmbH Deutschland

Project volume:
€ 25,000,000

Project description

The 368 m long Petersberg tunnel (route 3010 Koblenz – Perl) will be replaced using the tunnel-in-tunnel method.

This will be the first time this has happened in Germany whilst maintaining electrified operation.

To this end, Vössing – together with the executing work group – has developed the special suggestion of a continuous housing, which screens off the rail operation from the work areas, until readiness for execution.

Particular challenges were the approvable conception of the housing with an overhead conductor rail, very high loads from the tunnel expansion portal, which appeared as a result of blasting, and affected the foundations of the tunnel, and the specified short blocking period to assemble the housing.

The planning also included:

- Construction site installation in the flood zone of the Mosel incl. a pile foundation for the crane

- Demolition planning for the supporting walls

- Superstructure planning for the existing structure

- Special construction to fasten signal to a bridge pile

- Planning slope stabilisations under dynamic loads from the blasting

Engineering services

  • Project planning engineering structures, performance phase 1-5
  • Structural planning, performance phase 1-5
  • Specialist planning of technical equipment (OCL), performance phase 1-5
  • Project planning of traffic facilities, performance phase 5
  • Conception of protective housing until readiness for execution in project planning and specialist planning incl. overhead conduction bar
  • Design and measurement of slope stabilisations under dynamic loads from blasting
  • Design and measurement of a signal fastening on the existing bridge under dynamic load
  • Additional execution planning

Project impressions